Below is a real SWMP in which YPH features as the sole waste contractor. The site is an office extension and fit-out worth about £2m, the first wing of which was completed as shown with the second wing in early 2010. Note the final box.
SITE WASTE MANAGEMENT PLAN (SWMP)
|
Site |
Wynford House |
|
Start date |
19 February 2009 |
|
Completion date |
28 September 2009 |
|
Brief description of works
|
Site set up
Site plan and traffic management plan will be displayed in the office and canteen showing skip positions
|
Waste types and estimated quantities Rubble/hardcore - 2 skips over period of bricklaying Wood - 4 skips over duration of works (after start of roof) Cardboard/paper - 2 skips during fit out period Metal - 3 skips over duration of works Mixed other - 1 every 2 weeks Domestic (wheely bin) - 1 per month |
|
Waste Management Strategy |
||
|
Waste type & strategy |
Waste management site |
Waste management contractor |
|
Wood - arisings from roofing works and pallets deteriorating 8 yard skips to be transported to YPH |
Commercial recycling for chipping up and made into worktops Licence no EAWML/26043 Permit EPR/DP3496Sg |
YPH Waste Management |
|
Metal – reinforcing off cuts, bending materials, ceiling grid etc. 8 yard skips to YPH |
JC Thomas & Sons Metal Recyclers |
YPH Waste Management |
|
Paper/Cardboard – packaging mostly and office waste 8 yard skip to YPH |
Perry’s Recycling at Marston Magna No license – exempt |
YPH Waste Management |
|
Rubble – brick and block arisings and waste matter 8 yard skip to YPH |
Bulked up at YPH yard then available FOC to builders or removed and screened by outside contractors for reuse. |
YPH Waste Management |
|
General/Mixed waste – 8 yard skip to YPH |
Skip taken to YPH yard – skip is emptied and segregated as far as possible. Non-recyclable to Westcombe landfill site. License No. EAWML26022 |
YPH Waste Management |
|
Training During all site inductions the site plan displaying the location of the various segregated skips and recycling is shown. |
|
Materials Handling |
|
|
Materials most susceptible to damage |
Measures in place to reduce or eliminate damage |
|
Multigold bricks |
Delivered and stacked by the lorry tight to the fence in the compound. Brought out by forklift and loaded out by hand. |
|
Bags of cement |
Delivered on pallet, broken down by labourer and placed towards the back of our container. |
|
Windows |
Subcontractor supply and fit only when site is fully ready to receive. |
|
Doors |
Come wrapped and protected. Labourer to take immediately into building and store in suitable area. |
|
Monitoring Arrangements Reports gathered from YPH on segregation, also a number of skips used to compare to original estimate. Target is minimum 80% waste diverted from landfill. |